Government of Canada / Gouvernement du Canada
Symbol of the Government of Canada

Search

Output-Based Pricing System Regulations

Version of section 32 from 2024-01-01 to 2024-11-26:


Marginal note:Electricity generation facility

  •  (1) Subject to subsection (2), the gross electricity generated during a compliance period by each unit within the electricity generation facility, from each of the industrial activities set out in paragraphs 38(a) to (c), column 1, of Schedule 1 that is engaged in at the unit, is determined as follows:

    • (a) if a unit uses only one fossil fuel to generate electricity, in accordance with subsection 1(1) and section 2 of Part 38 of Schedule 3; and

    • (b) if a unit uses a mixture of fossil fuels or a mixture of biomass and fossil fuels to generate electricity, in accordance with subsections 1(2) and (3) and section 2 of Part 38 of Schedule 3.

  • Marginal note:Choose not to quantify

    (2) The person responsible for the electricity generation facility may choose not to quantify part or all of the quantity of electricity generated from one unit or a group of units.

  • SOR/2023-240, s. 20

Date modified: