Government of Canada / Gouvernement du Canada
Symbol of the Government of Canada

Search

Canadian Energy Regulator Pipeline Damage Prevention Regulations – Obligations of Pipeline Companies

Version of section 4 from 2020-03-16 to 2024-11-26:


Marginal note:Information – application for authorization

 If a person that intends to construct a facility across, on, along or under a pipeline, engage in an activity that would cause a ground disturbance within the prescribed area of a pipeline or operate a vehicle or mobile equipment across a pipeline has made a request to the pipeline company for the information that is necessary to make an application to the Regulator for authorization, the pipeline company must, within 10 working days after receiving the request, give the person all the information, and provide all reasonable assistance, that is necessary to prepare the application.

  • SOR/2020-50, s. 41

Date modified: